Frequently Asked Questions (FAQ'S)

Design

Design is expected to be done by the end of 2023. Permits are anticipated in the first quarter of 2024. After public bidding and award of contract, construction is anticipated to commence in the second quarter of 2024, and last approximately one and a half years with final connections to public services anticipated in late 2025.

Wells may remain operational for irrigation purposes, but they must be severed from the potable water service to the house. No cross connections are permitted. 

Construction

The sanitary sewer will be located along the road centerlines. Any driveway impacted by the construction will be replaced.  A public meeting will be scheduled during the design process and some these questions may be addressed.  It is too early to forecast construction impacts precisely at this time. 

Financial

Individual costs are unknown at this time; however, grants will be sought by the Village to reduce assessment costs.